Question: A part is processed in the following sequence: Machine B > > Machine A > > Machine C . Machines A , B , and

A part is processed in the following sequence: Machine B >> Machine A >> Machine C. Machines
A, B, and C are known to have scrap rates of about 2%,3%, and 4%.
(a) If 1000 units of the part must be produced each day, approximately how many parts must be
processed by Machine A each day? Show work. (15 points)