Question: A part requires two machining operations ( I and II ) on a milling machine. 8 0 0 0 units are to be produced per

A part requires two machining operations (I and II) on a milling machine. 8000 units are to be produced per month (20 working days). The factory operates 8 hours per day. The following information is known.
\table[[Operation,Standard Time,Efficiency,Reliability,Scrap],[I,2.8min,90%,90%,3%