Question: A particular project has only 4 work packages and the following data were collected during the execution of the project. Work Package Total Quantities Planned

A particular project has only 4 work packages and the
following data were collected during the execution of the
project.
Work
Package
Total
Quantities
Planned
Productivity
Rate / Unit
Installed
Quantity
Actual
Hours
1.1300 Sq. Mt 3 Hours 1001200
1.24200
Quantity
1 Hour 22002300
2.160 Ton 10 Hours 20200
2.2460 Sq. Ft 2 Hours 60340
Scenario Question - Answer question from the below scenario
Q) What is the current productivity index of this project?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!