Question: A particular stakeholder has a reputation for requesting many changes on projects. What is the BEST approach a project manager can take at the beginning
A particular stakeholder has a reputation for requesting many changes on projects. What is the BEST approach a project manager can take at the beginning of the project to manage this situation?
a
Say No to the stakeholder a few times to dissuade him from submitting more changes.
b
Talk to the stakeholder's boss to find ways of directing the stakeholder's activities to another project.
c
Ask that the stakeholder not be included in the stakeholder listing.
d
Get the stakeholder involved in the project as early as possible.A particular stakeholder has a reputation for requesting many changes on projects. What is the BEST approach a project manager can take at the beginning of the project to manage this situation?
a
Say No to the stakeholder a few times to dissuade him from submitting more changes.
b
Talk to the stakeholder's boss to find ways of directing the stakeholder's activities to another project.
c
Ask that the stakeholder not be included in the stakeholder listing.
d
Get the stakeholder involved in the project as early as possible.A particular stakeholder has a reputation for requesting many changes on projects. What is the BEST approach a project manager can take at the beginning of the project to manage this situation?
a
Say No to the stakeholder a few times to dissuade him from submitting more changes.
b
Talk to the stakeholder's boss to find ways of directing the stakeholder's activities to another project.
c
Ask that the stakeholder not be included in the stakeholder listing.
d
Get the stakeholder involved in the project as early as possible.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock