Question: a permit is obtained on friday aug 1, the material are to be delivered aug 8 the material are needed labor begins on aug 11

a permit is obtained on friday aug 1, the material are to be delivered aug 8
the material are needed labor begins on aug 11
it is estimated 15 days of labor are required
the crew will work everyday including weekends and holidays
the project is scheduled to be completed on sep 8.
how many floating days are available for this project?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!