Question: A PERT / CPM activity has an optimistic time estimate of 3 days, a most likely time estimate of 1 2 days, and a pessimistic

A PERT/CPM activity has an optimistic time estimate of 3 days, a most likely time estimate of 12 days, and a pessimistic time estimate of 18 days. The expected time (in days) of this activity is: hint: formula is available in lecture notes
 A PERT/CPM activity has an optimistic time estimate of 3 days,