Question: A Pizza store is planning to redesign its layout. The precedence relationship for preparing a pizza meal is given in the table below. The demand
A Pizza store is planning to redesign its layout. The precedence relationship for preparing a pizza
meal is given in the table below. The demand for the pizza is pizzas in an eight hour shift.
a Draw precedence diagram of this process.
b Given the demand, what is the cycle time?
c Suggest an efficient layout and compute efficiency of the process.
Task Description Predecessor Time
minutes
A Shape the dough to form the
crust
None
B Add the pizza sauce A
C Add the cheese B
D Add the sausage C
E Add the pepperoni C
F Package the pizza DE
G Label the package F