Question: A plant operates on Just - in - Time / lean principles. The total production requirements for next three days are 3 0 0 0

A plant operates on Just-in-Time/lean principles. The total production requirements for next three days are 3000 units of X,300 units of Y, and 1200 units of Z. Assume that the plant has enough capacity to produce all of the units within the three-day period. Which one of the following plans best represents uniform plant loading for this plant?
Question 29 options:
none of the choices are correct
Produce 3000 units of X first, then 300 units of Y, and then 1200 units of Z during the three-day period.
Produce 1500 units of X on day 1,1500 units of X on day 2, and then 300 units of Y and 1200 units of Z on day 3.
Produce 3000 units of X on day 1,300 units of Y on day 2, and then 1200 units of Z on day 3.
Produce 1000 units of X,100 units of Y, and 400 units of Z each day for the three days.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!