Question: A plastics company is considering two injection molding processes. Process X will have a first cost of $500,000, annual costs of $200,000 and a salvage

A plastics company is considering two injection

A plastics company is considering two injection molding processes. Process X will have a first cost of $500,000, annual costs of $200,000 and a salvage value of $100,000 after 5 years. Process Y will have a first cost of $800,000, annual costs of $150,000 and a salvage value of $250,000 after 5 years. Use Equivalent Worth Method (choose one method). ROUND OFF ANSWER TO THE WHOLE NUMBER A. Process X: B. Process Y: C. Which process should the company select