Question: a. Please identify the critical path(s). (2 points) b. Which activity or activities would you crash? (2 points) c. what is the total crash cost?

a. Please identify the critical path(s). (2 points)

b. Which activity or activities would you crash? (2 points)

c. what is the total crash cost? (2 points)

d. Please identify the new critical path(s) after crashing the schedule. (4 points)

a. Please identify the critical path(s). (2 points)b. Which activity or activitieswould you crash? (2 points)c. what is the total crash cost? (2

A (1 Day] D (4 Days] H (6 Days) B [2 Days) E (5 Days) F (4 Days) 1 (5 Days] K (4 Days] G (6 Days] J (4 Days) C [4 Days)The Crash Costs and Crash Days (number of days able to be crashed) of each activity are listed in the table below. Task Crash Cost Crash Days A N/A 0 B N/A 0 C 4000 2 D 3000 E 2000 2 1000 G 3000 H 4000 2 5000 2 4000 2 K 2000 If you have to reduce the overall project schedule by 3 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!