Question: a. Please identify the critical path(s). (2 points) b. Which activity or activities would you crash? (2 points) c. what is the total crash cost?
a. Please identify the critical path(s). (2 points)
b. Which activity or activities would you crash? (2 points)
c. what is the total crash cost? (2 points)
d. Please identify the new critical path(s) after crashing the schedule. (4 points)


A (1 Day] D (4 Days] H (6 Days) B [2 Days) E (5 Days) F (4 Days) 1 (5 Days] K (4 Days] G (6 Days] J (4 Days) C [4 Days)The Crash Costs and Crash Days (number of days able to be crashed) of each activity are listed in the table below. Task Crash Cost Crash Days A N/A 0 B N/A 0 C 4000 2 D 3000 E 2000 2 1000 G 3000 H 4000 2 5000 2 4000 2 K 2000 If you have to reduce the overall project schedule by 3 days