Question: A Poisson flow line has three stations with mean effective process times ( 3 , 2 , 5 ) . Assume a closed system. (
A Poisson flow line has three stations with mean effective process times Assume a
closed system.
a pt Consider and Compare the best CT and TH versus the CT and TH for
the Poisson line. Hint: the best CT and TH are obtained in a deterministic world.
b pts What is the minimum amount of WIP for the Poisson line that would result in a TH that
is at least of the best TH What is the associated CT for this WIP level in the Poisson line?
c pts Consider a reduction of in the bottlenecks mean effective process time. What are
the new CT and TH for and
d pts Now consider a reduction of in the mean effective process time at each non
bottleneck station. The bottlenecks process time remains at its original level. What are the
new CT and TH for and
e pts If there is an improvement from the actions in
explain why it is surprising given the
behavior of deterministic lines and why it is important.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock