Question: A power company can develop a hydroelectric project at one of two capacity levels, 1 MW or 2 MW , at the cost of $
A power company can develop a hydroelectric project at one of two capacity
levels, MW or MW at the cost of $ billion, or $ billion, respectively.
Construction in either case takes year's time, with the cost being incurred
immediately. If the smaller capacity is chosen, it is not possible to increase
capacity at a later date. The company can sell the capacity from MW on
a contractual basis for a net revenue of $ million per year in perpetuity
with payments beginning in years' time ie year after the construc
tion period No customer will currently purchase the second megawatt of
capacity, but a second party eg another state or country will contract to
purchase the second megawatt of power for $ million per year in perpe
tuity beginning years from now with the first payment at the end of that
year
a Find the NPV of building for each capacity level if the interest rate is
Should the power company invest in or MW of capacity?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock