Question: A Printed Circuit Board ( PCB ) machine installs integrated circuits onto a board. Before starting to produce a board, the PCB machine requires a

A Printed Circuit Board (PCB) machine installs integrated circuits onto a board. Before starting to produce a board, the PCB machine requires a 4-minute
setup. This 4-minute setup time is fixed and is independent of the number of boards to be produced later. Once in production, the PCB machine processes the
boards one by one, and spends 3 seconds on each board. The batch size the PCB machine uses is 100 boards/batch.
The capacity of the PCB machine =
boards/minute.(Round off your answer to the FIRST decimal point)
(Difficulty Level - Hard)
Type your answer....203 points
Consider a stage doing batching process with a setup. The curve below depicts the relation between the batch size and the stage capacity. Which of the option below
correctly describes the meaning of the curve? (Difficulty Level - Easy)
Stage capacity increases in batch size proportionally.
Stage capacity increases in batch size. But the marginal improvement has a decreasing trend.
Stage capacity increases in batch size. The marginal improvement also has an increasing trend.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!