Question: A priority matrix is . . . . A ) A list of significant events that occur over the life of the project B )
A priority matrix is
A A list of significant events that occur over the life of the project
B A document that authorizes the project manager to initate and lead the project
C A definiton of the end result or mission of your project
D A document which identifies the priorities of a project. Which of them are constrained, which are enhanced and which can be accepted.