Question: A private car maintenance centre operates a two-step process for car maintenance. Tomorrow's work will consist of inspecting seven cars as shown below. Time (hours)
A private car maintenance centre operates a two-step process for car maintenance. Tomorrow's work will consist of inspecting seven cars as shown below.
Time (hours)
Order Step 1 Step 2
A 1.20 1.40
B 0.90 1.30
C 2.00 0.80
D 1.70 1.50
E 1.60 1.80
F 2.20 1.75
G 1.30 1.40
a. Determine a job sequence that will minimize the time required to completion. (15 marks)
b. Describe the advantage of forward and backward scheduling, and its impact to productivity. (15 marks)