Question: A Process Breakdown Structure can provide a reasonable alternative to a Work Breakdown structure for an extensive development project if Multiple Choice phase exit criteria

A Process Breakdown Structure can provide a reasonable alternative to a Work Breakdown structure for an extensive development project if
Multiple Choice
phase exit criteria are firmly established.
there are appropriate predecessor relationships in place.
deliverables are tightly aligned to milestones.
tangible products are being developed.
risk planning is included early in the project.