Question: A process for a product has p=.53% If it is desired for an LQL=5% and the lot size is 7500, the appropriate Dodge-Romig plan is:

A process for a product has p=.53% If it is desired for an LQL=5% and the lot size is 7500, the appropriate Dodge-Romig plan is:

A) n=185, c=5, AOQL=1.7%

B) n=150, c=7, AOQL=2.9%

C) n=150, c=3, AOQL=5.6%

D) n=185, c=5, AOQL=2.7%