Question: A process in being evaluated for stability using X bar R chart. The sample size is 4 and sampling frequency is 2 hours. No of

A process in being evaluated for stability using X bar R chart. The sample size is 4 and sampling frequency is 2 hours. No of subgroups taken for calculation of control limits are 15. The Grand Average is 100 and Average Range is 7. What are the control limits for X bar and R chart ?
A
UCL x-bar =121 LCL x-bar =79 UCL R =21 LCL R =0
B
UCL x-bar =105.10 LCL x-bar =94.89 UCL R =15.97 LCL R =0
C
UCL x-bar =101.56 LCL x-bar =98.439 UCL R =11.57 LCL R =2.43
D
UCL x-bar =114 LCL x-bar =86 UCL R =14 LCL R =3.5