Question: A process includes 9 tasks and there are 3 workers. Each task can be assigned to only one worker and each worker must be assigned

A process includes 9 tasks and there are 3 workers. Each task can be assigned to only one worker and each worker must be assigned consecutive tasks. The time to complete tasks 1 to 9 (in seconds) are as follows: 60,45,25,45,30,15,50,70,55 Instruction: Round your answer to one decimal place. What is the capacity of this process in units per hour? Units per hour Applications are scanned in a process with two resources. The first resource has a capacity of 0.38 applications per minute. The capacity of the second resource is 0.17 applications per minute. Demand for this process is 0.22 applications per minute. Instruction: Round your answer to three decimal places. What is the cycle time of this process (in seconds)? seconds