Question: A process includes 9 tasks and there are 3 workers. Each task can be assigned to only one worker and each worker must be assigned

A process includes 9 tasks and there are 3 workers. Each task can be assigned to only one worker and each worker must be assigned consecutive tasks. The time to complete tasks 1 to 9 (in seconds) are as follows: 60,70,25,30,50,15,25,70,75 Instruction: Round your answer to one decimal place. What is the capacity of this process in units per hour? Units per hour