Question: A process includes 9 tasks and there are 3 workers. Each task can be assigned to only one worker and each worker must be assigned

A process includes 9 tasks and there are 3 workers. Each task can be assigned to only one worker and each worker must be assigned
consecutive tasks. The time to complete tasks 1 to 9(in seconds) are as follows:
80,75,25,15,60,30,30,80,90
What is the capacity of this process in units per hour?
Note: Round your answer to 1 decimal place.