Question: A process includes 9 tasks and there are 3 workers. Each task can be assigned to only one worker and each worker must be assigned
A process includes 9 tasks and there are 3 workers. Each task can be assigned to only one worker and each worker must be assigned consecutive tasks. The time to complete tasks to 9 (in seconds) are as follows: 40, 90, 35, 35, 50, 5, 10, 80, 60 Instruction: Round your answer to one decimal place What is the capacity of this process in units per hour? Units per hour
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts