Question: A process includes 9 tasks and there are 3 workers. Each task can be assigned to only one worker and each worker must be assigned

A process includes 9 tasks and there are 3 workers. Each task can be assigned to only one worker and each worker must be assigned consecutive tasks. The time to complete tasks 1 to 9( in seconds) are as follows: 45 55 15 25 50 5 30 95 50 What is the capacity of this process in units per hour?