Question: A process includes 9 tasks and there are 3 workers. Each task can be assigned to only one worker and each worker must be assigned
A process includes 9 tasks and there are 3 workers. Each task can be assigned to only one worker and each worker must be assigned consecutive tasks.The time to complete tasks 1 to 9 (in seconds) are as follows: 80, 65, 35, 20, 25, 45, 30, 85, 80
What is the capacity of this process in units per hour?