Question: A process is accomplished in 4 sequential steps- S1, S2, S3 and S4. The lead times (in minutes) and the number of resources for every
A process is accomplished in 4 sequential steps- S1, S2, S3 and S4. The lead times (in minutes) and the number of resources for every step are indicated in the table below.
Sub - Process Time (min) No of resources
Sub process/Time/Resources
S1 12 1
S2 8 1
S3 16 2
S4 10 1
Assuming infinite demand, what is the process flow rate? {keep the time dimension as minutes for this, and answer in decimals)