Question: A process is accomplished in 4 sequential steps- S1, S2, S3 and 54. The lead times in minutes) and the number of resources for every

A process is accomplished in 4 sequential steps-
A process is accomplished in 4 sequential steps- S1, S2, S3 and 54. The lead times in minutes) and the number of resources for every step are indicated in the table below. Time Sub- Process No of resources (min) S1 12 1 S2 8 1 S3 16 1 S4 10 1 If customers arrive at a constant rate of 3 customers per hour, what is the utilization of S3? (answer in decimals)