Question: A process is ___________ constrained if the implied utilization of any resource is above 100%. a.supply b.demand c. bottleneck d. inventory
A process is ___________ constrained if the implied utilization of any resource is above 100%.
a.supply
b.demand
c. bottleneck
d. inventory