Question: A process is designed to produce 2 comma 3 0 0 units per hour. The process has a scrap rate of 1 . 4 %

A process is designed to produce 2 comma 300 units per hour. The process has a scrap rate of 1.4% and a 13% inherent inefficiency. Assuming that the actual output of the process is 2 comma 425 units per hour, what is the process design capacity, available capacity, actual capacity, capacity utilization, efficiency and the output gap for this process?
Part 2
The design capacity is
enter your response here units per hour. (Enter your response as a whole number.)