Question: A process is in control at X=100, R-bar = 7.3 with n=4. If the process level shifts to 101.5 with the same R, what is

A process is in control at X=100, R-bar = 7.3 with n=4. If the process level shifts to 101.5 with the same R, what is the probability that the next X point will fall outside the old control limits? Circle the correct answer:

  1. 0.016
  2. 0.029
  3. 0.122
  4. 0.360