Question: A process requires 6 tasks, #1-#6, that must be performed in that order. Currently there are 3 employees that are equally skilled at each task.

A process requires 6 tasks, #1-#6, that must be performed in that order. Currently there are 3 employees that are equally skilled at each task. Employee A is assigned tasks 1 and 2, employee B is assigned tasks 3 and 4 and employee C is assigned tasks 5 and 6. The task times (all in seconds) are given in the table. TasksActivity time (seconds) 70 40 40 30 35 15 o Uk WN Suppose the system started without any work in process inventory (i.e., an empty system). How long would this process take to produce 10 units (in seconds)