Question: A product needs to be processed on both Resource X and Resource Y. There is only one of each of these resources and your goal
A product needs to be processed on both Resource X and Resource Y. There is only one of each of these resources and your goal is to meet market demand, which is 20 units per day and a day has 12 hours of working time. It takes 30 minutes to process a unit on Resource X and 15 minutes on Resource Y.
Based on the market demand, the capacity utilization ratio for Resource X is equal to _________
A. 100%
B. 83%
C. 120%
D. 67%
E. 50%
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
