Question: A production process for a product involves the following steps, some of which can be done in parallel. The process includes the possibility of rework
A production process for a product involves the following steps, some of which can be done in parallel. The process includes the possibility of rework if defects are found:
- Material Preparation: 1 hour
- Cutting and Shaping happening at the same time:
- Cutting: 1.5 hours
- Shaping: 2 hours
- Assembly: 2 hours
- Inspection: 1 hour (10% need rework)
- Packaging: 0.5 hours for small parts (30%) and 1 hour to large parts (70%)
What is the Core Process Flow time in hours (2 decimals)
STEP 1: Draw Process Map.
STEP 2:Compute Work Content of Each Activity.
STEP 3: Identify Paths and Compute Total Work Content of Each Path and Identify Critical Path.