Question: A production progressprocess consists ofa one step machine operation. The scrap rate is 1 0 % for this operation. After the price process improvement if

A production progressprocess consists ofa one step machine operation. The scrap rate is 10% for this operation. After the price process improvement if the scrap rate for operation could be reduced by30% at this operation, if the desired monthly output is 1,000 units, how many units would this save in terms of the scrap allowance