Question: A production system with one machine has the following interarrival and service times. Make a simulation by event of all the parts to obtain the
A production system with one machine has the following interarrival and service times. Make a simulation by event of all the parts to obtain the requested performance indicators:
Part Interarrival time Service Time 1 4 2 4 5 3 4 7 4 5 7 5 4 7 6 3 6 7 4 3 8 3 5
Step by step simulation included in the Excel file and answer: the simulation ends in minute (with number) Average number of parts in queue at any time (round to two decimals if needed) Utilization of the machine (in decimals and round to two decimals if needed)