Question: A program has 20% branch instructions of which 60% are not taken branches. what is the effective speedup we could obtain from a 5 stage
A program has 20% branch instructions of which 60% are not taken branches. what is the effective speedup we could obtain from a 5 stage pipeleine if we stall use the pipeline with branch penality ? Assume ideal CPI is 1.
1)2.48
2)2.99
3)3.125
4)4.24
5)none
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock