Question: A program manager is trying to advise the owner on which project dellvery method would be best for their upcoming iport expansion. They have stated
A program manager is trying to advise the owner on which project dellvery method would be best for their upcoming iport expansion. They have stated their key project goals include:
An expedited project schedule.
Colaboration between the primary parties including the owner, the designers, and the builder
Shared risk amongst the primary parties
Which of the folloking delivery methods should be recommended?
O A Design Bid Build DBB
O B Construction ManagementAtRisk CMAR
O C Agency Construction Management
O D Integrated Project Delivery PD