Question: A project charter typically does not authorize the project manager to use organizational resources to complete the project. A . True B . False 4
A project charter typically does not authorize the project manager to use organizational
resources to complete the project.
A True
B False
A commonsense approach to improving the coordination between project plan
development and execution is to follow this simple rule: Those who will do the work should
not plan the work.
A True
B False