Question: A project consists of six consecutive tasks that have average duration and worst-case duration estimates (in weeks) as shown in the table. Use Newbold's method
A project consists of six consecutive tasks that have average duration and worst-case duration estimates (in weeks) as shown in the table. Use Newbold's method to determine the aggregated two sigma buffer for this project.
| Activity | Average | Worst-Case |
| A | 10 | 14 |
| B | 2 | 4 |
| C | 6 | 12 |
| D | 8 | 13.5 |
| E | 9 | 12 |
| F | 5 | 7.5 |