Question: A project consists of six consecutive tasks that have average duration and worst-case duration estimates (in weeks) as shown in the table. Use Newbold's method

A project consists of six consecutive tasks that have average duration and worst-case duration estimates (in weeks) as shown in the table. Use Newbold's method to determine the aggregated two sigma buffer for this project.

Activity Average Worst-Case
A 10 14
B 2 4
C 6 12
D 8 13.5
E 9 12
F 5 7.5