Question: A project construction is set to start in October. Based on historical records, the chance of sunny weather is 2 5 % , and the

A project construction is set to start in October. Based on historical records, the chance of sunny weather is 25%, and the chance of an early winter is 35%. With sunny weather, construction will cost $175,000. With an early winter, the building will cost $200,000. If the weather is between the two extremes, construction will cost $190,000. What is the probability distribution for the construction cost?
113,750
$189,750
303,750
190,000