Question: A project contains 4 paths. The expected duration (days) and variance for each path are shown below. Path Path Expected Duration Path Variance ABCD 10

A project contains 4 paths. The expected duration (days) and variance for each path are shown below.

Path Path Expected Duration Path Variance
ABCD 10 7.2
AXYZ 13 3.7
AGHI 6 2.1
AEFG 9 14.3

We expect the project will be completed within X days 95% of the time. What is X?

Group of answer choices

20.25

16.77

19.07

16.15

None of the answers provided are correct within 0.5 days.