Question: A project costs $264.91 and subsequent cash flows for dates 1 through 3 are $36.60 , $56.88 , and $51.91 , respectively. If there is
A project costs
$264.91and subsequent cash flows for dates 1 through 3 are
$36.60,
$56.88, and
$51.91, respectively. If there is only one more cash flow at date 4 , and the project's internal rate of return is
7.75%, what is the amount of the date 4 cash flow? Round your final answer to 2 decimal places and leave out the "$" sign.

A project costs $264.91 and subsequent cash flows for dates 1 through 3 are $36.60, $56.88, and $51.91, respectively. If there is only one more cash flow at date 4 , and the project's internal rate of return is 7.75%, what is the amount of the date 4 cash flow? Round your final answer to 2 decimal places and leave out the "\$" sign. A project costs $264.91 and subsequent cash flows for dates 1 through 3 are $36.60, $56.88, and $51.91, respectively. If there is only one more cash flow at date 4 , and the project's internal rate of return is 7.75%, what is the amount of the date 4 cash flow? Round your final answer to 2 decimal places and leave out the "\$" sign
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts