Question: A project estimator returns the following estimates for the final phase of a project. Optimistic: 1 3 0 hrs Most Likely: 3 2 0 hrs

A project estimator returns the following estimates for the final phase of a project.
Optimistic: 130hrs
Most Likely: 320hrs
Pessimistic: 360hrs
Using the standard bell-curve weights for a three-point estimate, what do you calculate the total time to complete this phase will be?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!