Question: A project estimator returns the following estimates for the final phase of a project. Optimistic: 1 3 0 hrs Most Likely: 3 2 0 hrs
A project estimator returns the following estimates for the final phase of a project.
Optimistic: hrs
Most Likely: hrs
Pessimistic: hrs
Using the standard bellcurve weights for a threepoint estimate, what do you calculate the total time to complete this phase will be