Question: A project has 12 activities: A through L (A, B, C, D, E, F, G, H, I, J, K, and L). This project has two

A project has 12 activities: A through L (A, B, C, D, E, F, G, H, I, J, K, and L). This project has two critical paths: A-B-C-D-G-L and A-E-F-H-I-L. Which one of the following activities can have slack greater than zero?

A) F

B) G

C) K

D) H

E0 None of these are correct