Question: A project has 3 activities ( in row ) where the duration and the immediate predecessors of each activity are provided in the following table.

A project has 3 activities (in row) where the duration and the immediate predecessors of each activity are provided in the following table.
1. Determine the expected duration of the project (1.5 points).
2. determine the Variance ^ of the project duration (1.5 points).
The rubric
Correct answer Correct formula & wrong answer Wrong formula or no attempt
For any part/problem 100%50%0
Note: You get the points if all the calculations are done in the cells of this excel sheet.Tasks Duration immediate predecessors
a = Optimistic time m = Most likely time b = Pessimistic time
16910-
23451
34682

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!