Question: A project has 9 activities ( tasks ) where the duration and the immediate predecessors of each activity are provided in the following table. 1
A project has activities tasks where the duration and the immediate predecessors of each activity are provided in the following table. Determine the duration of the project. Determine the critical activities, ie what activities are the critical activities? Determine the slack time of Activity