Question: A project has a $ 6 0 0 total budget to deliver 6 deliverables of equal value spaced evenly over six months. After four months,
A project has a $ total budget to deliver deliverables of equal value spaced evenly over six months. After four months, three deliverables were completed at a cost of $ SPI is:
$
$