Question: A project has a $ 6 0 0 total budget to deliver 6 deliverables of equal value spaced evenly over six months. After four months,

A project has a $600 total budget to deliver 6 deliverables of equal value spaced evenly over six months. After four months, three deliverables were completed at a cost of $200. SPI is:
125%
75%
-$100
$100