Question: A project has a C P I > 1 . 0 and an S P I 1 . 0 . This would indicate the project
A project has a I and an I This would indicate the project is:
A behind schedule with a cost savings
B ahead of schedule with a cost savings
C behind schedule with a cost overrun
D ahead of schedule with a cost savings