Question: A project has a unit price of $20.98, a variable cost per unit of $8.97, fixed costs of $312,920, and depreciation expense of $38,009. Ignore
A project has a unit price of $20.98, a variable cost per unit of $8.97, fixed costs of $312,920, and depreciation expense of $38,009. Ignore taxes.
What is the cash break-even quantity?
a. 26,055.0
b. 24,642.7
c. 25,093.5
d. 26,569.2
e. 24,564.7