A project has an asset beta of 0.70. The expected return on the market is 18%, and
Fantastic news! We've Found the answer you've been seeking!
Question:
A project has an asset beta of 0.70. The expected return on the market is 18%, and the relevant risk-free rate is 7%. The project's required rate of return is
(A) 14.7%
(B) 24.5%
(C) 19.6%
(D) 10.5%