A project has been defined to contain the following list of activities along with their required times
Fantastic news! We've Found the answer you've been seeking!
Question:
A project has been defined to contain the following list of activities along with their required times for completion.
Activity No. | Activity | Time (weeks) | Immediate Predecessors |
1 | Collect requirements | 3 | |
2 | Analyze processes | 2 | 1 |
3 | Analyze data | 2 | 2 |
4 | Design processes | 6 | 2 |
5 | Design data | 3 | 3 |
6 | Design screens | 2 | 3,4 |
7 | Design reports | 4 | 4,5 |
8 | Program | 5 | 6,7 |
9 | Test and document | 7 | 7 |
10 | Install | 2 | 8,9 |
a. Draw a network diagram for the activities.
b. Calculate the earliest expected completion time.
c. Show the critical path.
d. What would happen if activity 6 were revised to take six weeks instead of two weeks?
Related Book For
Introduction to Accounting An Integrated Approach
ISBN: 978-0078136603
6th edition
Authors: Penne Ainsworth, Dan Deines
Posted Date: